IRAQ - TURKEY CRUDE OIL PIPELINE SECOND EXTENSION

LOCATION
Yumurtalık - Ceyhan, Turkey

CLIENT
STK/LCP Joint Venture

CONTRACTOR
-

COMMENCEMENT
March 1986

COMPLETION
January 1987

This major project consist of the construction works of second Iraq-Turkey pipeline, the new tank farm, modification works at the existing tank farm, Ballast Water Treatment Plant and extension of the existing jetty.

Tekfen Engineering carried out the following tasks:

  • Application drawings of tank foundations, site design, infrastructure, and steel construction, including 5 x 135.000 m3 capacitiy floating ceiling tank area.
  • Detailed and application drawings of piping, site lighting, drainage, telephone, grounding, instrumentation works.
  • Detailed and application drawings of connections with the old tank area, various pump and equipment foundations and complete design of control building including supervising services during construction.
  • Detailed drawings of small jetty in the crude oil loading jetty.
  • Application drawings of Ballast water treatment plan.
  • HVAC design